Cloud Control 12.1.0.5 : It’s production upgrade day…

cloudI mentioned a couple of months ago I was planning to upgrade our production Enterprise Manager Cloud Control installation from 12.1.0.4 to 12.1.0.5. Well, today was the day. I held back a while because I knew I would be out of the country for a while on the Latin America tour and I didn’t want to make a big change before I ran away. :)

So today I pretty much did exactly what was in my upgrade article and everything went well. I upgraded the OMS and the local agent and I’ll run like that for a couple of days before I start pushing out the agent updates to the monitored hosts.

Happy days!

If you are interested, you can see some of my Cloud Control articles here.

Cheers

Tim…